You do not need to excavate or lay a foundation for a stock tank pool. You should, however, level the area where you plan to put the stock tank. Also, stock tanks full of water and people can get heavy, so do not place them on a deck or other raised structure that could collapse from the weight.

Yes, small pool leaks are fixable with waterproof patches and sealants. It is always best to avoid draining a pool if you can, since doing so safely takes time, patience, and a whole lot of water to refill it. Larger pool leaks may require draining, but in this case, it's best to call in a professional.

The total time to install an inground pool typically ranges from 8 weeks to 4 months. This timeline can be influenced by several factors, including permitting, site preparation, and the construction process itself.

Key phases and their typical durations include:

  • Permits: Obtaining necessary permits can take anywhere from two to six weeks.

  • Excavation and Site Preparation: This phase takes about a week but can be extended by problematic soil, unexpected ground conditions, or the need to move underground utility lines.

  • Construction: The actual build, including plumbing and electrical work, often takes one to two months. The pool material is a major factor here; a concrete pool needs about 30 days to cure, while installing a fiberglass or vinyl liner is much faster.

External factors can also cause significant delays:

  • Contractor Availability: Spring and summer are busy seasons, and high demand can lead to long waitlists, potentially adding months to your start date. It is often recommended to start planning and getting estimates up to a year in advance.

  • Other Delays: Weather, material shortages, complex designs, and other unforeseen challenges can extend the project timeline.

Completely refreshing the water in an aboveground pool every five to seven years helps keep it free of bacteria and algae. Emptying the pool also allows you to clean, repair, or replace the pool liner. Schedule your water change when the weather is mild, as intense heat or cold can damage the pool liner when the pool is empty.

If you want your pool to be ready for summer, spring is the perfect time to put in an inground pool. However, if you are concerned about cost and are looking to save money, you can wait until fall and winter, when some companies may offer discounts on pools and pool materials.

The Boyd, WI homeowners’ guide to above ground pool installation services