"In July we signed a contract. Darrell said he would start in September and the day after Labor day his crew showed up and started building the breeze way for the new tiny house. By the end of the week the breeze way was built and footers were poured for the house. The next weekend block was laid. Framing started within the minimum time allowed for block to cure. His crew had it framed, roofed, and windows in by the end of September.
After the framing was completed my wife and I decided there was not enough room on first floor for a bedroom. We were thinking of adding a bedroom in basement. Darrell recommended we add bedroom to the side of the building. Good decision. He had the 12' X 12' addition framed and roofed within two days. This was done in middle of October.
Rough plumbing was started and completed within a week along with rough electrical which took about two days.
Building was insulated as soon as rough ins were completed which took one day. Drywall followed right after the insulation was done. Drywall was completed around Halloween.
Initial painting took about a week and then floor installed. This was completed by Thanksgiving.
Finished plumbing and electrical completed around 1st of December.
Touch up painting and hvac were completed by 2nd week of December.
Daughter and grandkids moved in new tiny house December 23. Merry Christmas.
Darrell time line is impeccable.
"