Top-rated deck maintenance specialists.

Get matched with top deck maintenance specialists in Cloverdale, IN

Enter your zip and get matched with up to 5 pros

Need a pro for your deck maintenance project in Cloverdale, IN?

Select your specific project to find the pro for you.

Find Deck maintenance specialists in Cloverdale

Avatar for Maximus General Contracting LLC
Maximus General Contracting LLC
4.4(
135
)

Serving Cloverdale, IN and surrounding areas

In business since 2000

Free estimates

Emergency services offered

"Eric and his people are very professional.  Eric is very nice and promptly to our request.  He fixed our roof on last Saturday since it was raining on Sunday. He also gave us good advice about our roof maintenance.  The fixing price he gave is very reasonable.  We will definitely use him when we replace our roof next time and recommend him to our friends as well.
"
Recommended by92%of homeowners
Avatar for Legacy Window & Door LLC
Legacy Window & Door LLC
4.1(
151
)

Serving Cloverdale, IN and surrounding areas

Free estimates

Emergency services offered

Credit card accepted

"After receiving a few other estimates on a sunroom addition plus a screened in porch, we decided to go with Legacy Windows. Mark’s estimate was in the middle of the other estimates and he offered much more flexibility than the other companies we spoke to in terms of customization. He is a great salesman with previous marketing experience. We signed our contract on April 10th. We were told that Mark and his crew were finishing a room and would be able to start in 2-3 weeks with a timeframe of 6-8 weeks for completion of our room addition project. The budget and timeframe worked well for us, so we decided to add replacement windows for the rest of our house (11 windows total). Several weeks went by and our project had not yet started so we followed up with Mark. We were told that there were issues with his current project (did not pass inspection) and it would push our start date back due to the workmanship repairs. During this time period before any work began on our project we would communicate often with Mark to check on the status of our project. The really frustrating thing about working with Mark is his inability to fulfill commitments he would make to us in regards to project timing and when things would be done. Our primary communication with him was via text messages and time after time he would tell us, “we should be starting next week” or “we are going to be making up for lost time quickly” and time would pass and it just wouldn’t happen. Work on our project began when our existing windows were replaced in early June. The foundation for the expansion was finally started in late June and framing started in early July (roughly 3 months after signing the contract). The first crew completed the framing, hired the shingles out, installed some of the cedar siding, and installed one wall of windows. We were seeing decent progress after having such a long wait in the beginning, all the while the commitment issue just kept popping up. We would get a text saying something like, “going to be at the house tomorrow with some stone samples” and he wouldn’t show up. It was annoying, but progress was being made and we were happy with how the expansion was taking shape so we were willing to overlook it. Sometime toward the beginning of August (roughly 4 months after signing the contract), work just stopped. Again, when we would reach out to Mark asking about the status of our project we would be told, “I’ll have an action plan later this afternoon” or “we want to get everything we done we can this week” or “the crew will be there tomorrow and we will be working all week on your project trying to finish”. In the meantime, nothing would be done and we would repeat the process. This went on for over 3 weeks, during this time there was absolutely no work done. Large piles of construction trash and building materials sat in our yard during this time. A great deal of the usable wood began to warp and I am sure that ultimately materials had to be tossed from being left in the elements for so long. After a couple weeks I finally moved a significant portion of the usable wood up onto the deck so it would at least be partially protected. We found out that there was an issue with the electrical and Mark had decided to let Crew #1 go as they were not meeting his expectations, but it was not communicated to us until the end of the over 3 week period. A second crew then arrived who Mark said usually only did work for him on the south side of Indy (we live in Lebanon), but he wanted to get our project back on track. There seemed to be little to no communication between the crew and Mark on what they were supposed to work on so we had to explain to them what was in the contract to be completed. Crew #2 also started making good progress, they finished the cedar siding, got the rest of the windows installed in the sunroom as well as installing the sunroom ceiling. About this time, which was at the beginning of September we had a separate crew come out to do the drywall. Mark recommended them very highly. As it turned out, the drywall was not properly installed or insulated (in some walls there was no insulation), and ultimately it had to be taken down and redone by Crew #2. Crew #2 seemed to be doing a really good job and we were quite pleased with their progress and the quality of work they were doing for us. They were replaced by Crew #3 sometime in mid-September. We were never told why they were replaced, but Crew #3 was much closer to where we lived so I assume that had something to do with it. Much like when Crew #2 started, there seemed to be little communication between Crew #3 and Mark on what they were supposed to work on. So we again had to explain what was in the contract to be completed. All through the process, the commitment issues mentioned previously continued. We were not as happy with the quality of the work done by Crew #3 as we had been by Crew #2 (or even Crew #1), but they did finally complete for the project for us and after (3) failed attempts we finally received a pass from the building inspector on his final inspection. When Crew #3 decided they were finished they never came back, we communicated multiple times with Mark about the remaining punch list items to no avail and ultimately decided to finish most of the small punch list items ourselves instead of waiting any longer for them to finish (clean up, sanding / finishing drywall, etc.). We love the way the sunroom and covered porch area turned out. From contract signing until the end it took a little over six months, but in Mark’s defense he did agree to let us add a brand new window in the dining room of our house to tie everything together at no cost to us as appreciation for our patience. There are things that we liked about Mark’s company and things we didn’t, I have tried to summarize each category as follows: Positives • Price seemed reasonable • It is truly a custom build, no problem with changes we had at any point • Love the way it turned out, looks amazing • Mark seemed to genuinely care about the quality of the product he was delivering to us (he replaced the cedar shakes that had been installed by Crew #1 because he wasn’t happy with the quality Negatives • Our project seldom felt like it was a priority, part of the reason it took so long was because they were over committed on other projects • Commitment Issues (addressed previously) • Construction Trash left in our yard for months • We cleaned up inside more than they did, I understand drywall work is messy. They never swept up any of the dust and they didn’t clean up any of the clumps of dried drywall mud all over the floor. • We finished some of the minor punch list items, just to be done."
Additional Photos
Additional Photos
Additional Photos
Additional Photos
Additional Photos

+70

Recommended by84%of homeowners
Avatar for HLM Landscape
HLM Landscape
4.0(
4
)

Serving Cloverdale, IN and surrounding areas

In business since 2023

Free estimates

Emergency services offered

"HLM Landscape really did an awesome job removing a tree from our house and also removing four other mature trees on the property. I would highly recommend their services. They were very polite and went beyond what was required of them."
Flower Garden
Deck Demo
Custom Deck Build
Custom Deck Build
Custom Deck Build

+17

Response time8 hrs
Response rate100%
Recommended by75%of homeowners
Avatar for Oakley Construction
Oakley Construction
3.9(
7
)

Serving Cloverdale, IN and surrounding areas

In business since 1999

Free estimates

Emergency services offered

"I'd highly recommend them. Our roof was put on quickly and they were professional and very reasonable in pricing. We were explained things every step of the way and are very happy with the way it turned out! We've hired them to build a new deck for us next!"
Additional Photos
Additional Photos
Additional Photos
Additional Photos
Additional Photos

+21

Recommended by83%of homeowners
Avatar for E&M Express Construction - Home  Facebook
E&M Express Construction - Home Facebook
2.9(
9
)

Serving Cloverdale, IN and surrounding areas

In business since 2019

Free estimates

Credit card accepted

"The work was very good. The price was reasonable. The job was done in a timely manner. They were very about keeping in touch about when the job would be done the progress."
Response time20 mins
Recommended by80%of homeowners
Showing 1-10 of 36
Deck Maintenance questions, answered by experts

The best material for your deck depends on several factors, including your budget, location, aesthetic preferences, and the level of maintenance you’re willing to do. Wood decking, like redwood, ipe, cedar, and pine, lasts the longest, but it’s more expensive and requires more upkeep than composite and synthetic decking.

When building a deck, #2 grade lumber is a go-to for several reasons. It’s strong, budget-friendly, and works well for most framing and decking needs. But upgrading to #1 or Appearance Grade can give your deck that extra visual edge if you're after a cleaner, more polished look for high-visibility spots.

Staining and sealing the underside of a deck creates a moisture barrier but traps water in the boards, quickly leading to rot. No matter how well you seal the above deck, water still gets through via nails and screw heads on the surface. Allow this water to flow naturally under the deck, where it is routed through the drainage system.

Yes, adding a composite deck, such as one made from Trex, can significantly increase your home's value. It is a valuable home renovation for recouping costs, with some estimates for return on investment (ROI) ranging between 60% and 70%. More recently, Remodeling's 2024 Cost vs. Value Report suggests a deck addition has an ROI of 82.9%, with an average resale value of nearly $14,600. A new deck makes your yard more functional, enhances the landscape's aesthetic, and can entice prospective buyers. The investment may have a higher return if the deck adds usable square footage to the property.

Yes, you can build a deck over your outdoor HVAC unit, but you need to leave at least 5 feet of vertical clearance above the unit. If you don’t want your deck to be that high off the ground, you could build a floating deck in another part of your yard—again, as long as you leave at least 4 feet of horizontal space between the deck and your AC unit.

The Cloverdale, IN homeowners’ guide to deck maintenance services

From average costs to expert advice, get all the answers you need to get your job done.