First, Dannex worked on our home in Fredericksburg, Virginia. All information is factual and has been shared with Dannex, via email, texts, video, and photos. Dannex broke ground on my project on July 8, 2020, with a contractual agreement to be finished within 120 days (~November 4th) and promised before Thanksgiving. They failed. I was compelled to terminate the contract on December 11, 2020, because of breach of contract in time of completion, quality of work, and the material adverse effect on the use and enjoyment of our home. For the past week, I have been using vacation time, and I have spent $4,900 on other contractors to finish or correct what Dannex was paid to do, so we can have our home ready for Christmas. My project with design costs ~$174,000, of which I have paid about $150,000. Dannex bills and demands payment quickly, so I expected the same in performance, but they did not. My project was not plagued with weather delays, nor the unavailability of materials. Dannex was the delay. They worked ~50 days sporadically, and much of that was only on weekends and holidays as if we were a side job. Dannex was hired to extend the kitchen, add a sunroom, and porch, and a room in the basement. Initially, the material delivery, the concrete work, and the framing went well, and then it came to a screeching halt. The material was on site, but no laborers. We had plans for the kitchen at Thanksgiving when promised. Yet and still, we have not had a working kitchen for more than 5 months. Poor project management has been the Achilles heel of this project. The PM seemed oblivious to project management, and the Dannex president seemed uncaring. Every holiday and some weekends between July 8 and Thanksgiving Day, that is when Dannex mainly worked at my house. Lots of blundering amateur mistakes, but I will only mention the big ones, otherwise I would be writing all day. 1. July 10: Water flowed into my basement because they dug my water softener system and sump pump spouts from the French drain, that I had installed. The water flowed into the house. 2. July 21: Dannex ripped the roof open to connect the addition, and then they left. When I arrived home from work, I could look up and see the sky from my kitchen, until the torrential downpour started. It stormed inside our house. Water flowed from the ceiling, through the recess lights, down the walls through the house intercom system, and flooded the whole second level floor. From 7:PM to after midnight, we mopped, emptied 5-gallon buckets, and pushed out as much water as we could. By the way, that intercom system is costing us $1,672.52 to replace. 3. August 24: Dannex removed the 22-foot external kitchen wall (not scheduled) to connect the buildout. They left the house open to the elements Any flying animal could have come right in, and the mosquitoes ate us up for the next few days. At 4:30 it started raining. Their framers got stuck in the rain and mud in my backyard at 5: PM. I notified the PM, via text. He responded to me and said, "I cannot babysit grown-ass men." 4. September 8, 2020: I informed Dannex that the cooktop hood flue was not centered on the cooktop and the cabinets had to shift right, and their measurements were off because electrical outlets would be over the cooktop. They ignored it, and now that is a major holdup to having a functional kitchen. 5. December 14: County inspector arrived, the kitchen failed inspection due to no flue and exhaust for a gas cooktop. The same day, I took vacation time to rip it up and reinstall the new vinyl kitchen floor that Dannex poorly installed. Two times subcontractors told me they had not been paid at all after months and mentioned a mechanics lien on my property, Dannex told them that I had not paid. Up to that date I had paid Dannex over $130K on time, but Dannex lied putting my home in jeopardy. Obviously, they were ta...