Concrete Project On May 3, 2024, Sandra signed a contract with Addison Deal, to provide; -Stamped concrete walkway 6.5 ft x 40 ft - concrete slab 32ft x 50ft -concrete slab 12.5ft x 35ft -stairs 4ft x 40ft -retaining wall 5ft x 25ft -regrade and seed the lawn that is disturbed by the construction. The terms of this agreement was $45,550 with 50% down payment and the balance due upon completion. On May 6, Addison proposed an extension of the contract to include - concrete driveway 328ft x 14ft 6 inches thick with rebar -clearing underbrush at the road perimeter -planting trees and bushes The terms of this agreement was $48,216 with 50% down payment and the balance due upon completion. The job was expected to be completed within 2 weeks Mr. Deal and 4 workers worked three days, May 7, 8, 9 and did not appear on Friday 10. Mr. Deal told us later that he had a family matter. On Monday, May 13, he brought a relative who had a team of landscapers who began clearing underbrush and dead trees. They worked on May 14. On May 15, Mr. Deal said that he needed a draw on the remaining funds of $14,000 to purchase concrete. I reminded him that we were expecting to pay the remaining money on completion of the job. He said that concrete must be paid in advance. I hesitated but eventually I wrote on the contract that I was advancing $14,000 and he and I signed it. I wrote the check to the name of the company “The A Team” and he said that the check must be written to him or the bank would not accept it. I questioned that but then I rewrote the check to Addison Deal and I put the company name in the memo. The check was designated for concrete. I did not see any member of the team or workers for 5 days. On Tuesday, May 21, through Friday, May 24, the Construction workers cleared the area for the two concrete pads and did landscaping work. During this time, a separate verbal agreement was made for a total of $3,000 specifically for landscaping as additional trees needed to be planted at the end of the driveway. On Friday, Mr. Deal came to Sandra and said that he needed a draw on the funds of $20,000 for concrete because the concrete was ordered for May 28 and May 29. I refused to write another check and a long discussion ensued. Eventually, Sandra wrote out expectations for each day and both Sandra and Mr. Deal agreed that a bobcat was to be brought in to lower the level of the driveway to accommodate the 6 inch depth and with the $20,000 he would purchase: -concrete -color for the stamped walkway -stamp -rebar And all work was to be completed by the end of the week of May 28, 2024. Both Sandra and Mr. Deal signed this agreement and Sandra wrote the check for $20,000. When Mr. Deal left, he said that the concrete truck would be on the property at 7:00 AM on Tuesday, May 28. No truck and no workers came in the morning on Tuesday May 28. When Sandra sent a text asking for status, Mr. Deal responded, saying that the concrete could not be confirmed because he was not able to pay the bill before the concrete company closed on Friday, May 24, so the new date for the concrete would be Monday, June 3rd. Additionally, Mr. Deal told me that he would provide the name, phone number, and confirmation number for the concrete. He did not provide this information. Mr. Deal and 4 workers came later in the day on Tuesday, May 28, to prep the driveway. However, instead of bringing the bobcat to lower the driveway, they rolled out a layer of wire mesh down the length of the driveway and laid various loose pieces of mesh near the garages. When Sandra completed work for the day, she looked at the work and sent a text to Mr Deal questioning the wire mesh, because the driveway and pad was supposed to have rebar. Mr. Deal called Sandra and said that no, this was incomplete, that the end result was going to have plastic, then wire mesh, and then all covered by rebar. He sent pictures to her via text to show what the completed prep work would look like. Neither Mr. Deal nor his workers came back to the jobsite for the rest of the week. On Monday, June 3rd, no concrete truck arrived. When Sandra texted and asked about the status, Mr. Deal replied that the concrete company had pushed them back to Tuesday, June 4th, so that they could have the concrete with fiber in it. He provided the phone number to the concrete company as proof. Sandra called the concrete company and found out that Mr. Deal had not paid for the concrete by the prior Friday. He had called and tried to pay by a cash app which the company could not accept. According to the concrete company, if Mr. Deal paid for the concrete by noon that day, then concrete would be delivered at 7AM the following day. Additionally, according to the concrete company, they closed at 4, so payment was required by that time for any delivery at all the next day. Sandra texted and asked Mr. Deal if he would respond once the payment was made, and he replied in the affirmative. At 3PM, Sandra texted again requesting status but he did not respond. Sandra called the concrete company at 4PM, and they responded that he had not paid but had requested that they stay around for a little while after closing hours because their GPS had them arriving at 4:12PM. Cheryl from the concrete company called Sandra at 4:40 stating that they had not arrived and she was leaving for the day. Later, at 4:54, Cheryl called back and said that he had arrived and had paid for 20 yards of concrete, but that because he was so late, the concrete would be delivered at noon the following day, rather than the 7AM timeslot. On Tuesday, June 5th, workers arrived midmorning. Sandra and I had noticed that the forms for the steps were not square, so requested that the workers correct the forms. The workers tried to correct the forms. Later, however, when the concrete was poured and reviewed, professionals noted that the forms were still not square. Concrete arrived around 1PM, and it was noted that, although fiber had been promised, no fiber had been requested. Sandra called the concrete company for the second truck (10 yards of concrete per truck) and paid the extra $65.00 for fiber to be added to the second truck. The workers poured the concrete for the steps and walkway along the back of the house. Sandra had a friend, Jesse, who works with concrete at the house while the concrete was being poured, and he noticed that the work was not of professional quality, as the concrete was poured, but the edges were not cleaned up, so that once the forms would be removed, the edges would be rough. The workers proceeded to pour the concrete pad for the patio at the back of the house. As they had not used any rebar, Jesse had them place some of the wire mesh that had been set down by the garage as part of the base. However, as they laid the concrete, because they had not done adequate prep work by laying down plastic, the concrete got hard before it was laid properly. At the same time, Mr. Deal left the property for several hours. He returned with an additional concrete smoothing tool/brush. Between the steps, walkway, and patio at the back required only about 7 yards of concrete, and the remaining amount needed to be poured, according to the concrete truck driver. The workers filled a wheelbarrow with concrete and brought the wheelbarrow up to the front of the house to lay the sidewalk. However, the sidewalk was supposed to be a different color of concrete, so Jesse and Sandra stopped the worker from using that concrete for the sidewalk. Instead, Jesse requested that the remaining amount of the concrete be poured at the far back of the space by the garage. Sandra, Jesse, another friend that we called, and the concrete truck driver, poured and worked with this remaining concrete. The construction workers were still at the back of the house working with the patio. Meanwhile, the second concrete truck, which had arrived around 2PM was still waiting to be poured. As this had been sitting for several hours and the construction workers were not ready for the concrete, Sandra and Jesse turned the concrete truck away, refusing delivery. At this point, Sandra told Mr. Deal that the concrete work w