CrownHandyman
About us
I DO NOT RETURN PHONE CALLS. EMAIL ME AT [email protected] COVID 19 update: I am only working outdoors or in homes when no one is there until the pandemic is sorted out. I can no longer keep up with phone calls. Email me. I work by appointment only. I do small jobs only. I come look at the work. I provide you with an estimate. If you like the estimate we schedule a time for me to come do the work. I show up on time. I am skilled in many aspects of construction. My specialty is doors. I do carpentry, plumbing, electrical, and drywall. I repair things.
Business highlights
Services we offer
Carpentry, decks, doors, drywall, electrical, hanging cabinets, lattice work, painting., tile, windows, wood rot repair. Plumbing
Amenities
Free Estimates
Yes
Accepted Payment Methods
- CreditCard
Number of Stars | Image of Distribution | Number of Ratings |
---|---|---|
97% | ||
0% | ||
0% | ||
3% | ||
0% |
Filter reviews by service
Excellent ideas on redesigning two bathrooms to update them and keep them looking appropriate for a house in a historic district.
The Bad:
The completed bathrooms as a finished product are average at best and unsatisfactory in several ways. The tile work is amateurish. The paint job in the bathrooms is so thin that you can see the original paint color bleeding through in many areas. The electrical work on one of the circuits did not work and was dangerous. (They fixed that.) The plaster work is uneven, has burrs and looks bad in many places. The baseboards and quarter round trim are separating from the wall and from each other especially in the corners. The toilet paper holder is loose in one of the bathrooms.
The Ugly:
This project was supposed to go as follows: Do the first bathroom to completion, then move to the second bathroom and the entire project would take about 6-8 weeks. I was pushed by them to do both bathrooms at once, I relented and allowed them to do that because, according to them, it would be "more efficient". If "more efficient" is defined as taking 16 weeks, then it was. I find it particularly annoying that on many of the days, only 4-5 hours were spent working on the bathrooms. They maintained a mid morning to mid afternoon workday. This increased the number of days required for the project. Because they did both bathrooms at once, we had to clear out closets so that they would have access to plumbing and share the one remaining functional bathroom. This extended the number of days that we were inconvenienced on the project dramatically. On top of all that, the work area was a complete mess. Tools, materials and debris were strewn about the entire third floor. We found the minimal time spent on the job each day and the mess to be incredibly disrespectful.
As they started the project and began the demolition, they did not turn off the main water line. This is an old house with brass pipes that have failed. As the second floor toilet was being removed the pipe that supplies water to it broke and flooded into the dining room below. That room had been recently painted and renovated. They did a lousy job of repairing the damage on the ceiling and crown molding. It looks awful. This accident was easily prevented and reasonably expected. This mess means we get to have the entire ceiling in the dining room repainted and the crown molding repaired.
On top of all this, at about the ten week mark, when we were no where near completion, I expressed my dissatisfaction with how things were going. Rather than change how things were going, they packed up and quit the job. After a couple of days of drama and discussions they returned and finished the work.
The Aftermath:
After the project was deemed to be finished and they had left and been paid, we found a number of problem areas that I have already described. What looks like mistakes and carelessness to us has been characterized as a 'punch list of little things that still needs to be done" by them. We disagree. Tile that has been poorly installed is a mistake. Walls that have had one extremely thin layer of paint applied is carelessness. Electrical outlets that do not work are both. If a contractor is going to insist on being paid on completion, it seems reasonable to us that the work is done to completion and satisfaction. There is nothing in the agreement about "punch lists" of items found to be lacking that will be completed at some undetermined date after the project is completed. If you tell me you are finished, I expect you to be finished to our satisfaction.
I am sure they do a fine job at handyman services. Remodeling projects are beyond their abilities. We cannot recommend them for projects that require more than a few days.
"When we started this job (remodeling 2 bathrooms in a 100 year old house), the client was given a projected finish date. After the job was underway, we encountered plumbing problems beyond the scope of the job. We performed and were paid for these items. During the course of the job, the client made changes to the remodel involving moving of plumbing fixtures and additional tile work. These changes added considerable time and expense to the job. The client was happy and complimented us on the work being performed. On the original projected completion date, I got an email from the client saying that the quality of the work was excellent but he was not happy with how long the job was taking. What followed was a parade of flaming emails (sometimes several a day) with a litany of complaints about absolutely everything. It became so intense that the crew left the site taking their tools with them for fear of being locked out. It took more than a week to work out how to get this job finished and done well. That was our only concern. We did finish the job and were paid in full. We had a projected date to start a third bathroom in the same house (an estimate had been submitted and approved). We went to meetings to work out the details. We expected to take care of the remaining punch list on the first job when we returned to do the third bathroom. Then 3 or 4 days before the start date, I got an email from the client saying he was going to go with another contractor and his review appeared on Angie’s List. I have uploaded a picture of some of referred to in the client’s review. Please read our other reviews."
A new washer and dryer were delivered while Thom was working in the condo. (I was there as well.) The delivery people brought the wrong electrical cord for the dryer, so they were going to leave the washer/dryer in the condo and come back on another day to install them. Thom persuaded them to wait in the condo while he went to Home Depot and exchanged the wrong cord for the right one. It was the persuading part that impressed me. This was one episode at any rate where it was useful to have Thom on the premises to help in dealing with another service provider. By the way, Thom didn't charge me for this time-consuming intervention.
With respect to punctuality, it may be worth saying that Thom arrived exactly on time, to the minute, neither early not late. I mention this mainly because it is something that I can report on that is measurable and objective. (I was always the first or only job of the day. It might be different if he was coming from another job.)
Licensing
State Contractor License Requirements
All statements concerning insurance, licenses, and bonds are informational only, and are self-reported. Since insurance, licenses and bonds can expire and can be cancelled, homeowners should always check such information for themselves. To find more licensing information for your state, visit our Find Licensing Requirements page.
*Contact business to see additional licenses.