The initial visit with the sale rep, David N., went well. We were given the details we needed for the deal at the time (free upgrade to Del Mar package + free installation (retrofit only, not new construction). We were only able to take advantage of half of that deal, as our windows had to be new construction, but we knew that going in so that is not against AVW.? Their first team was punctual, but surprisingly understaffed for the number of windows being done. The rest of the crew arrived on day 2. There were two separate "teams" within the full crew: one from the Bay Area, led by a fellow named Ryan, and the other from their Simi Valley offices named Ignacio (they colloquially referred to him as "Nacho", but I won't do so since he is a real person, not a tortilla chip with cheese on it).? Initially things went smoothly. They went approximately three windows at a time, removing the old, removing stucco, and preparing the space for a brane new window. Our windows and doors have alarm wiring going to them, and we were told they wouldn't have any problems with that (not true, as you'll see later). It took about three days to get the downstairs windows and doors put in (we have a total of 12 windows and 2 patio doors for our house!), and then the upstairs windows were started. And then began the problems.? Partway through the installation process for the upstairs windows, the Simi Valley team (lead by Ignacio) was recalled back down to Southern California where they were from, leaving us with only four remaining crew members, two teams of two workers each, led by the aforementioned Ryan. Up to this point Ryan had kept us in the loop about what was going on and what to expect, and oversaw the overall project while doing the work of cutting and sizing materials for the other technicians to use in the installation of the windows.? I had noticed that the second patio door was initially installed with no wood paneling underneath on one side and that it was not completely level or sealed well. So I asked Ryan to take a look and make sure the work had been done properly. Unfortunately this was not the case. The patio door was installed with no new wood paneling underneath, with one third of the underside completely bare (no wood), the middle looking "OKish", and the right third of the area underneath the door with rotted wood left in place. This would have made it very easy for rain to get under our house and cause erosion and/or mold issues down the line, so I told Ryan that this needed to be taken care of. But that wasn't the only issue downstairs.? Both patio doors needed to be re-shimmed with proper spacers, insulated, and sealed. So Ryan and the three remaining crew members had to take them back off and redo the entire install by themselves because the Simi Valley crew had left already. This put the project behind schedule by at least a day at that point. It should be noted that the Simi Valley crew handled the removal and pre-installation steps themselves while Ryan's crew put the windows in and performed the finishing steps (for the most part, see below for more issues). I had noticed that the upstairs windows had no spacers, no insulation of any kind in the space between the stucco and framing, and were not level. I also noticed that there was unevenness around nearly all windows, both downstairs and upstairs where the space between the window frame and drywall was different with regard to the sides vs. the top and bottom. There was also noticeably sloppy caulking on these windows. The only windows not plagued by these quality issues were the ones done by Ryan and his partner, Cesar.? So Ryan had to again undo the window installation and retrofit spacers (shims) to make the windows level and looking good. At the same time, he told us that because we had gone with internal frame and casing on our garden window that the rest would look better with the same layout, so we decided to go along with that. Doing so, however, added more time to the project, resluting in Ryan's direct supervisor, Glenn coming out the following day to "help", because at that point Glenn had transferred two of the remaining four crew members from our project to a new project elsewhere, leaving us with only Ryan and Cesar to do all of the remaining work.? I say "help" because Glenn was so slow that only two windows were worked on by him, one being the kitchen window and the other being the one by our china cabinet. Both windows had leveling issues and the kitchen window looked awful due to the frame jutting out by more than an inch the entire perimeter of the window (as it replaced a windowsill). Ryan had to redo the framing so that there was a windowsill, as not doing so meant we would have an ugly frame around that one window. The end result though was better than I expected and had a windowsill long enough to hold my grandmother's tea cup set without them hanging over the edge.? Amidst all of this, the project was also delayed by three additional days because the building inspector was not called to come out on time and by the time the above supervisor called him to come out, it was Friday and the inspector couldn't arrive until the following Monday.? So after doing the downstairs windows, Ryan moved to the upstairs windows, where he had discovered lopsided windows and poor caulking. So once again, it meant removing and redoing the install properly with spacers, framing, and casing. So even more time was added to the project that was supposed to only take five days initially.? When that work was finally done on April 11th, we signed off on the completion certificate, fourteen days later, much longer than the five day install period was supposed to be. Then our troubles began in earnest.? We had our alarm installer (NSC Alarm Company) come out to reconnect the alarm to the windows. The window installers had drilled a hole through the frame of the window for the wire to come through, which was fine, but when the alarm technician connected the sensors, the zones did not register. He discovered that instead of simply pulling the wire to extend it to be long enough to go through the hole in the window frame, the window installers (Ignacio's crew from Simi Valley) had spliced the wires, which caused loss of signal and rendered our alarm unusable.? There was a small section on the contract not more than a few words that noted "not responsible for reconnecting alarm wiring. But that assumes that the window installers make no changes to the wiring (pulling out wire to extend it is not considered a change). Splicing is a direct alteration of the alarm wiring, which would thus nullify that clause/section. We'd have accepted the damage if it were incidental, not resulting from a purposeful alteration.? So we contacted AVW about the issue and were given the runaround. I finally contacted their corporate office in Simi Valley and spoke to a man named Jason there. He told us flat out AVW wouldn't cover the full cost of the repairs, but so far even after sending him a direct quote from NSC, we've heard nothing from AVW. And every time I call I'm told that Jason is not available or on vacation, and Brian, the general manager for the Santa Clara office, has not gotten back to me yet either. It's been two months of phone tag and waiting and we can't use our alarm.? This means that we can't get the window trim (indoors/outdoors) painted because the alarm company has to drill and drop new wire first, and we can't get that started until we hear back from AVW. So our house, and especially my grandfather, are now insecure with no readily available recourse as AVW is avoiding responsibility.? And as if that weren't enough, our garden window had to have its front pane replaced by Anlin, and the replacement has a 1" x 0.5" gouge in it and needs to be replaced again as well. Still waiting to hear from Anlin or AVW on that one for over a week now.? And to top all of that off, one of the AVW crew stole a swiss army knife from my downstairs bathroom medicine cabinet. I can only assume whoever did so was looking for prescription drugs as that's usually what you do looking for in