The project went well overall. From the date of the first contact on May 27, 2011, to the first meeting with Matt Breyer on June 8, 2011, to the receipt of the first proposal on June 22, I found that the communication with the company was positive. When I had questions that needed clarification, Matt and the crew were always able to answer my questions and explain the options. An amended proposal was prepared on July 28, 2011, and I confirmed then for an October 2011 build. The project was scheduled for 10/5-6, but had to be pushed back to start October 10th. Demolition of the porch and the foundation began on Monday, October 10, 2011. That afternoon John and the crew dug and prepped the footer for the new foundation. At 9 pm John returned with cement block solids. On Tuesday, Sam the mason arrived early to lay the blocks and completed three walls by the afternoon. On Wednesday, October 12, the mason and assistant returned to apply a parge coat of stucco to the exterior walls. On Thursday, I received a call from the secretary Stacy, saying that they wanted to let the masonry cure a few days before doing the new porch floor. There was some confusion about their receiving my check payment which I had mailed. Subsequent checks were either delivered by hand to the office, or given to the crew at the time requested and stated in the proposal. The week of October 17 was the most stressful for me, because I had to be out of town on a business trip. I had hoped that the project would be completed before I left on the trip, but that did not work out. While I was away, the Breyer crew did framing and joists on the porch, removed temporary supports, reinstalled the roof support posts, framed the cement walk and steps, and put the porch deck in place. They poured cement for the walk and new steps down to the garage. They put the existing railings in place. The week of October 24 I discussed with Jason and Jeremiah the railings, the things I noticed that needed attention or remedy, and discussed paint colors with Matt. He was prompt about replying to my calls or email questions. I provided lunch for the crew on that Monday, and noted that they did a good job of rebuilding the railings, painting, preparing the steps and grading the ground and spreading the remaining stones. On October 31, final painting and finishing details to the porch railings, balusters, smoothing out rough scrapes to the railings, and checking the door clearance for access to the storage room under the porch. There were some delays during the week of November 7th, due to schedule conflicts and rain. On Wednesday Jason and Matt added an additional coat of paint, and then dropped off an extension cord on Friday morning in preparation for finishing the carpentry adjustments on Saturday. On Tuesday, November 15, Matt was finishing the project and told me to make a list of the areas of concern, the "completion list" which I sent to him via email on November 19. On November 23 I observed evidence of attention to the areas I had identified, however the underside of the lower railing was still unpainted. Matt addressed the issue of erosion of loosened dirt and rain water spilling into the drain area near the garage door. On Friday, November 25, 2011, Matt came to do finishing touch-ups and covering nail holes with silicone. I gave Matt the final payment for the completion of the project.