What followed was the ten month nightmare. Nothing happened until 5pm on April 15th, when we received a phone call saying work would start on April 17th. We worked all day and most of the night shutting down the kitchen. No one arrived to start work until April 22nd. Our first indication of problems came quickly. On April 25th, Mr. Hicks informed us that, because of irregularities in the previous wiring, the electrical work, which had been quoted in the contract at $600. would now cost us $2,600. We asked for a breakdown of these costs based on the electrician's time sheets and hourly rate. WE NEVER RECEIVED ANY SUCH BREAKDOWN, AND VERY INTERESTINGLY, MR. HICKS NEVER MENTIONED THE SUBJECT AGAIN! Work proceeded very slowly. Many weeks we had one or two workers for only one or two days, we tried everything to speed things up but Mr. Hicks would always promise things and then fail to do anything. We have a dozen e-mails headed "another broken promise" By mid June it was obvious that by the time we left for our trip there would be no kitchen. We arranged for Mr. Hicks to have access to our condo and garage in our absence. His last words to us before we left were: "I give you my solemn promise that everything will be completed by the time you return" On June 14th While in China we received an e-mail invoice for $3,142.50 the payment due in the contract at "Substantial Completion" . Fortunately we did not pay this bill. We returned on June 25th. Virtually no work had been done in our absence. The cabinets were only partially installed, there were no counter tops, no appliances, no plumbing, no electricity and the floor was bare concrete. SO MUCH FOR SUBSTANTIAL COMPLETION! We told Mr. Hicks that we would not be paying this invoice until conditions were such that we considered, not him, the work substantially complete. It was at this time that we had to confront Mr. Hicks, in front of witnesses, and ask him, several times "Did you or did you not, make this or that statement? HIS ANSWER WAS THE CLASSIC; I DON;T RECALL, I DON'T RECALL. When asked why no work had been done his response was "It rained a lot in June."
Finally, the week of July 15th, we got some action. The granite was installed. but the cook top was not flush as was clearly shown in the drawings. When we pointed this out to Mr. Hicks, he blamed it on us saying we had not instructed the granite fabricator properly. We found this response to be unbelievable as the contract specifically forbid us to have direct contract with his subcontractors. He refused to accept responsibility and we had little option but to pay another fabricator $900. to correct his mistake. The fridge was installed but did not fit the previously installed cabinets. He again blamed us, saying we had ordered the wrong appliance. A somewhat bizarre response as we did not order the appliances, Mr. Hicks' company did! In the end we found it futile to try to reason with him, and after seeking legal advice, on July 29th we declared him in default of the contract. His response was to send us an invoice for $4,050. and threaten to place a lien on the property. Under the terms of the contract, we were required to give him 60 days to respond or correct the work. He did not respond and our last communication offering arbitration, a registered letter, was refused and returned to us. The 60 days is now over and we are proceeding to hire another contractor (this time recommended by Angie's list) to complete the work.
The purpose of this review, which we feel deals only with specific facts and not opinions, is to try to prevent what happened to us happening to others. Michael & Susan Parker.