HEDMAN CONCRETE INC
About us
Hedman Concrete Inc. is a locally owned business providing services throughout Pierce and South King County. Our contractors are able to complete projects, large and small, with solid craftsmanship for a great look and exceptional durability. We can build out a number of different features including patios, retaining walls and stairs. We offer our quality services at fair prices and are glad to provide customers with a free estimate for their project.
Business highlights
Services we offer
We offer a nearly unlimited range of concrete services.
Accepted Payment Methods
- CreditCard
| Number of Stars | Image of Distribution | Number of Ratings |
|---|---|---|
| 0% | ||
| 25% | ||
| 50% | ||
| 0% | ||
| 25% |
WE FIRED THEM> This is may opinion and account of the experience that hiring Hedman Concrete had on our basement remodel .And the fact that we ended up firing them and had to hire another firm to come out and overpour the floor that they poured, before we could continue with our remodel, is the reason that I give them and overall F RATING. In the middle of December of 2013 they came and jack hammered out our old cement basement floor. It took three days including a Saturday and Sunday, even though it was only suppose to take 2 days. They didn't do any prep work to mitigate the dust or noise from intruding into our upstairs living area. We had taken out the stairway to upstairs and had some plastic over the opening, but it didn't seal very well and we didn't think about the furnace ducts system being a potential problem. But it was. We had to put up with dust and extreme noise for three days. They left a lot of the smaller cement pieces mixed in with the dirt on the floor and just other smaller pieces, like they had gotten tired of working. There was a month delay to get our Building permit approved, and they were going to be busy doing other work so it didn't cause a problem initially, having to wait to pour the new floor. In the meantime we hired a general contractor to do the construction part of the rest of our remodel and he conferred with Jason Hedman and his crew on just what they were going to be doing and what we needed for it to be a good base for our remodel. When we were able to get Jason and his crew back in during mid January of 2014 to put in the vapor barrier and work on the support foundations and work around the chimney and furnace, they balked at having to do things. I had to nag them about cleaning up around the outer walls of the foundation and chimney and making the edges clean enough so that the new cement would be thick enough over the existing concrete that is wouldn't just break up once it was poured and cured. They had left broken edges and unlevel corners of the old concrete that were raised above were the new flooring level was suppose to top out .I had to bring up these issues more than once and someone would come out and do a few minutes work and then be gone without finishing much. Our general contractor figured out new ways to do the foundations for our support beams that required less work, and possible issues, and we decided to pour around our existing flooring under the furnace and hot water heater. We didn't have much confidence in Jason and his crew by this time. When it came to pouring the new floor Jason left most of the prep work to his crew of 2 younger guys. We had another contractor put in a French drain once we found that we had water level issue under the house, and we had new plumbing installed in the dirt floor as well. When Jason's crew put in the vapor barrier they cut a piece of plastic that fit the dimensions of the flat surface of the floor. But there were dips for a couple of support foundation footings and the lower edges around the outside edge of the foundation. So when it was laid out it didn't cover the entire surface of the floor to be poured over. Fortunately, as part of our general's bid, he had accounted for putting in a vapor barrier over the French drain, so he got our floor covered, because Jason crew didn't seem willing to do a good job and redo it. The pour seemed to go OK and only took a few hours. But no one came back for 2 days to attend to it or have a look at how it was setting up. And Jason only lives a couple of blocks down the street. Well the pour was REALLY BAD. It was extremely unlevel and dipped and rolled. It appeared to have been free hand leveled and the floor area is 30' x 35' with the chimney and furnace in the middle. There were differences of inches in height within a few feet along the edges and a constant variation all over the floor. Jason came out, and along with our General contractor surveyed the floor and he agreed that if we gave him a chance he would make it right. He had his crew, not himself, work on grinding the new concrete with an industrial gas concrete grinder. Extremely noisy and dusty and hot work. They did not do anything more to mitigate the dust or noise. We got fans and our general contractor helped seal up some air/dust leaks into our upstairs living area. But the gas flumes from the concrete grinder were almost lethal upstairs so we had to leave or open the house up and this went on for over 2 days. After they ground down the high spots that were higher than the plan for the floor, they got to the point were they were going to pour a skim coat over the low parts of the floor that were over an inch low, they mixed it out of bags and sort of feathered it out by hand. This product was suppose to dry in a few hours, but it didn't. Again this was done on the weekend and we didn't see anymore for a couple of days. But our general contractor was out on Monday and we all noticed that the skim coat mixture was still moist, and he knew enough to know that the patch was not any good. When he hit it with a hammer, 2 days after it was poured, it chipped and crumpled up and it was still not dry. I finally called Jason to come out on Wednesday to come and have a look, but I told him that I didn't have any confidence in his work and that I wouldn't be having him or his crew trying to repair it. Jason came out and didn't like what he saw and said he didn't understand why the patch hadn't dried correctly or why it wasn't hard and firm. We also pointed out that a lot of the floor was still unlevel, especially over longer distances. At any given point the floor could be only about a 1/4" high out of level to a point 3' away. But 3' from that spot it would be out of level 1/4' low out of level, making a 1/2" out of level within 6' and we needed a level floor to put in walls and put down flooring. It was a terrible experience, and we paid for the demolition and haul away and for his materials but we didn't have him do any more work and didn't pay him for the labor that it took to do the bad pour. We had to hire some else to pour a 3" over pour that totally changed the construction of the basement and caused numerous issues that changed the final results of our remodel in a negative way.
reLicensing
State Contractor License Requirements
All statements concerning insurance, licenses, and bonds are informational only, and are self-reported. Since insurance, licenses and bonds can expire and can be cancelled, homeowners should always check such information for themselves. To find more licensing information for your state, visit our Find Licensing Requirements page.
*Contact business to see additional licenses.