Dug 6' trench for special footing. Installed rebar and forms. Coordinated with plumber. Arranged inspection. Poured footings and step ups. Built stem wall and column. Coordinated with termite, packed, and laid visqueen. Arranged inspection. Poured slab. Coordinated with fireplace and electrical. Built walls and chimney. Arranged for crane to set 24' and 9' lintels. Installed rebar for walls and lintels. Arranged inspection. Poured lintels, wall cells, chimney cells, column cells, and gap around chimney. Laid glass block.